The first step in using Project this way is to add the Work column. To add a column in Project, simply right-click on a column heading and choose Insert Column. Here I have added Work to the Entry table next to Duration. Now if you skip over the Duration, set Work, then assign a resource, Project calculates Duration. If you also mark the task as Effort Driven , Project will know to continue to calculate Duration when you add or remove Resources in the future. You can change both the Effort Driven and Estimated property for a task by adding a column or using the Task Information dialog box double-clicking on a task.
Remember Me. Please enter your username or email address. You will receive a link to create a new password via email. Quick Links. Visit mpug. Written by Sam Huffman. Share This Post. You May Also Like. Calling All PMs! Customer Reviews. Leave a Reply Cancel Reply Your email address will not be published. Sign In. Lost Password. Lost Password Please enter your username or email address. To understand how the final day duration of 0. This starts at a.
In this case, the percentage of the full day is determined by the number of allocated segments compared to the total number of segments within the day. Image Source. Daryl Deffler is currently employed by a large insurance company where he provides project management, project scheduling tool, process, and standards consulting for an enterprise project management office comprised of about project managers.
He has over 25 years in the IT project management field with experience managing small projects to large programs. During this time he has also developed and taught classes in both project management and scheduling tools such as Microsoft Project , Primavera and ABT Workbench.
He has been employed in the IT industry since in additional roles, including software development, technical support and management across mainframe, midrange and PC platforms. For example, rather than complicating the issue with the fact that the project team is in New York, Denver, and India, set up the schedule as if the entire team is in one location. After all, when you think about it, the fact that one resource works 8 hours on Monday during East Coast time and another work 8 hours on Monday on India time, both resources are working 8 hours in the same day.
When doing shift work, you might try setting up the project calendar to cover the longest number of hours per day and every possible work day. Meaning, if the longest shift is 11 hours and some team members work M-Th for 11hours and others work Wed-Sat but only for 8 hours, set up the project calendar for M-Sat 11 hours per day. Identify where the problems are appearing, try to find ways to simplify as needed , experiment with work arounds, and go with what works. I wish you the best of luck.
Think outside the box. Review Title. Your Review. Sign me up for the newsletter. Remember Me. Please enter your username or email address. You will receive a link to create a new password via email. Quick Links. There are a lot of inconsistencies. So just how does Project really calculate Duration? So far, easy, right? Just wait. It gets more complicated. Daily Work Distribution The first step in understanding work distribution is to understand how Project divides the work across the days.
Time Segment Allocation The second step to understanding work distribution is being aware of how Project divides the work day. On Tuesday, the 2. But how is Project calculating the last or partial days? Partial Day Allocations Partial day allocations occur on the first or final day of work allocation when the remaining work is less than the calculated maximum.
What to Remember about Task Duration To summarize, Project calculates task Duration in two ways: The Duration for Fixed Duration tasks is simply the fixed duration value, regardless of when planned work is or is not distributed within that duration. Duration includes any business day with planned work.
Business days with zero planned work are NOT included in Duration. However, to really understand what Project considers a full day of Duration and how it calculates partial days of Duration takes an understanding of how Project distributes planned work.
Planned work is distributed using the following logic: Daily work allocation is calculated based on the Work, Assignment Units and Work Contour value. This determines the maximum hour allocation per day, the number of days across which work is allocated and the hour allocation for each day. The percentage of the full day is calculated based on how many of the work segments contain work compared to the total number of available work segments in the full day.